Davao Int’l Airport completes runway rehabilitation ahead of schedule

Davao Int’l Airport completes runway rehabilitation ahead of schedule

FLIGHT operations at Davao International Airport are set to return to normal following the substantial completion of runway repairs this Wednesday, May 8.

The Civil Aviation Authority of the Philippines Area Center 11 reported that the remaining works on the runway were completed on May 7 and an inspection was conducted to check all completed segments of the asphalt overlay repair.

Hence, the CAAP Area Center Manager Rex Obcena says,

“Some portions need minor rectifications wherein works will be conducted during the daytime when there are no flights in close coordination with the air traffic control tower.”

Nevertheless, the Notice to Airmen for this project is scheduled to be lifted tomorrow, May 9, or once all remaining concerns are adequately addressed. This is ahead of the original target date of May 31.

Since April 8, the DIA runway has been closed for four hours each day, from midnight to 4 in the morning, to expedite the rehabilitation process. This involves a 1,200 square meter affected area, including the removal of 2-inch thick damaged asphalt pavement, application of emulsified asphalt tack coat, laying of hot bituminous asphalt mixture, and repainting of existing runway markings.

 